PROJECT SOLUTIONS:

> Implemented Phased Program that included the restoration of the facade and parking slabs

PROJECT SERVICES:

> Post Tension Floor Slab
   Replacement

> Facade Restoration

> Field Quality Assurance

> Shoring Design

 

PROJECT MARKET:

> Institutional

> Healthcare

STRUCTURAL RESTORATION OF UPMC - VICTORIA GARAGE STREET

The University of Pittsburgh Medical Center (UPMC) Victoria Garage was built in 1967 as a three level parking structure. In August of 1973, UPMC extended the original columns to support a six story school of nursing above. In 1982, an extra level of parking was added between the school of nursing and the original parking structure.

 

In 2008, StructureTec completed an evaluation of the exterior facade at Victoria Garage to identify deficiencies in the exterior brick, metal curtain wall, and weatherproofing.

 

After conducting an updated study in 2012, significant structural deficiencies were identified in the post tension floor slab system. Approximately 75% of the tendons exposed between levels two through four and 1/3 of the exposed tendons in the upper level were loose or broken, directly correlating to the concrete deterioration found on the floor slab and ceilings. StructureTec provided UPMC with several options and budgets for the restoration of the concrete parking slabs and the replacement of the post tensioning reinforcement.

 

This led to a multi-year phased program of restoration, beginning with the restoration of exterior facade and temporary shoring of those floor slab areas considered at risk of failure. Based on the need to maintain the garage operations over the long term, UPMC chose to remove and replace all of the failing post tension floor slabs.

 

In order to properly execute the restoration plan in budget and on schedule, StructureTec prepared the post tension design. MEP engineers assisted with the modifications to the electrical and plumbing systems, and an architectural firm was brought in to assist with the interior design requirements.

 

StructureTec also developed plans for an additional entry point in the garage. Due to the scope of restoration and building modifications, detailed plans were submitted to the City of Pittsburgh for approval. The plans included removal and replacement of floor slabs and post tension concrete construction, details of the new garage entry and modifications to bring the garage into compliance with ADA.

 

The work was completed in an 18 month aggressive schedule which also included complete slab-on-grade replacement. During the entire construction process, challenges on site, including a tight urban space, required careful planning for deliveries and logistics. Significant quantities of sound barriers were installed to minimize demolition and construction sounds as well as provided an extensive amount of dust containment barriers given the presence of hospitals in the immediate vicinity of the structure. When completed, the new facility provided 572 spaces for use by UPMC and the University of Pittsburgh.

WHAT WE DO

StructureTec is a building  envelope, pavement, and roof consultant specializing in the waterproofing and restoration of existing building envelopes, roofs, pavement and concrete structures.

CONTACT US

Phone: 800-745-7832

FOLLOW US

tips and articles on engineering, design, restoration, and building envelopes LinkedIn

SUBSIDIARIES

Construction Services GroupSM A tier one roofing, building envelope, and structural restoration contractor Building Products GroupSM A leading manufacturer and supplier of specialty building products

"We provide the best solutions"

StructureTec Group